Jal Jeevan Mission - District Dashboard  - Sant Ravidas Nagar

       
Heirarchy / District Progress Reference
Total Block :
Total Panchayat :
Total Villages :
Population :
Households :
FHTC :
FHTC(%) :
Total HGJ Villages:
Total Certified :
Handed Over Villages :
GP level member :
VWSC/ Pani Samiti/ Water User Group :
Operation and Maintenance User :
Women identified for field test kit (FTK) testing :
Skilled Human Resources available in village :
UP Jal Nigam Old Scheme
Total Scheme :
Total Village :
Total OHT :
Schemes send to O&M Details
Total Scheme :
Total Village :
Total OHT :
Water Demand Daily(M3):
Water Demand Weekly(M3):
Water Demand Monthly(M3):
Water Supply Daily(M3):
Water Supply Weekly(M3):
Water Supply Monthly(M3):
Partial Complete Schemes Details
Total Scheme :
Total Village :
Total OHT :
Water Demand Daily(M3):
Water Demand Weekly(M3):
Water Demand Monthly(M3):
Water Supply Daily(M3):
Water Supply Weekly(M3):
Water Supply Monthly(M3):
Incoming Complaints/Feedback Received
All Complaints :
Close Complaints :
Pending Complaints :
Total Feedback Taken Details
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Total Pradhan Call Feedback
All Complaints :
Close Complaints :
Pending Complaints :
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
S.E.,(Division), Jal Nigam (Rural) Feedback Taken
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Chief Engineer, (Zone), Jal Nigam (Rural)
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Chief Engineer, (H.O.), Jal Nigam (Rural)
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Unit Co-ordinator (Technical), SWSM
Total Feedback Taken :
Satisfactory :
Partially Satisfactory :
Not Satisfactory:
Not Related to JJM :
Estimated Cost and Expenditure Details(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
ISA Activities
Total ISA Activities :
Total Photos Uploaded :
Total Videos Uploaded :
IEC Activities
WorkShop/Wall Writing Activities :
PHASE II Activity :
IEC Regional Language Activity :
IEC Outdoor Activities :
JJM Scheme Details Phase 1       Phase 2,3,5       Phase 4
Total JJM Scheme :
Total JJM Scheme Covered Village :
O&M Schemes
O&M Schemes:
O&M JJM Village :
O&M Schemes Integrate With Automation :
Automation Integrated Schemes
Automation Installed Scheme:
Integrated Scheme :
Integrated OHT :
Integrated Village :
Live Connected OHT :
Live Pump On OHT :
Last 2 days Water Not Supply OHT :
Regular Water Supply OHT :
Water supply less than 75% percent :
Water supply greater than 150% percent :
Automation Integrated Verified Schemes (EE E&M)
Integrated Scheme :
Integrated OHT :
Integrated Village :
Functional OHT Water Demand/Supply (Meter 3)
Water Demand Daily :
Water Demand Weekly :
Water Demand Monthly :
Water Supply Daily :
Water Supply Weekly :
Water Supply Monthly :
Automation Integrated SchemesReference
Sno. Scheme Status Pump Status Scheme Id Scheme Name Agency Name Covered Village Regular Water Supply Last Data Receive Date
Total 20 20
1 20012325 Bharatpur Multi Village Water Supply Scheme WELSPUN 2 2 02-08-2025 12:11 PM
2 20016991 Kharhgpur Water Supply Scheme WELSPUN 1 1 02-08-2025 12:11 PM
3 20023969 Magaini Water Supply Scheme GA INFRA - BABA (JV) 3 3 02-08-2025 12:10 PM
4 20023990 Basawanpur water supply scheme GA INFRA - BABA (JV) 3 3 02-08-2025 12:10 PM
5 20023997 NAGMALPUR Water Supply Scheme GA INFRA - BABA (JV) 2 2 02-08-2025 12:10 PM
6 20024003 Ismaila Water Supply Scheme GA INFRA - BABA (JV) 3 3 02-08-2025 12:10 PM
7 20024004 Mardanpur water supply scheme GA INFRA - BABA (JV) 2 2 02-08-2025 12:10 PM
8 20024005 Gobindpur water supply scheme GA INFRA - BABA (JV) 2 2 02-08-2025 12:10 PM
9 20024008 Abholi water supply scheme GA INFRA - BABA (JV) 1 1 02-08-2025 12:10 PM
10 20024009 Baraila water supply scheme GA INFRA - BABA (JV) 1 1 02-08-2025 12:10 PM
Components Wise Physical Progress
Sr.No. Components Target Achivement %
1 2 3 4 5
1 Tubewell 399 394 98.75
2 Pump House 399 372 93.23
3 Chlorination system 335 248 74.03
4 OHT 399 372/169 93.23
5 Distribution (Line Laying in Km.) 5439 5332 98.03
6 Solar Plant 385 293 76.10
7 F.H.T.C. 251779 241777 96.03
9 ROAD DISMENTLING/RESTORATION(KM) 1406 1382 98.29
10 Villages where 100 % road restoration completed 97070 60333 62.15
11 Comissioning of Village 997 583 58.48
12 Regular water supply 997 581 58.27
Agency Progress Details
Sr.No. Agency No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 GA INFRA - BABA (JV) 137 245 53796 50629 94.11% 170 69
2 Welspun Kaveri Infraprojects JV 262 752 183390 176800 96.41% 527 45
Total 399 997 237186 227429 95.89% 697 114